Bácsvíz

Energy savings at Bácsvíz Zrt.'s wastewater treatment plant in Kunszentmárton through program-level optimisation of aeration.

Project overview

Energy savings

~4 500

kWh/month

Capacity

700

m3/day

Our role

As main contractor, we supplied and operated the aeration optimisation technology: installation, maintenance, monitoring and remote supervision.

01

The client

Our client was Bácsvíz Zrt., a utility company; the project was carried out at the Kunszentmárton wastewater treatment plant.

02

What we did

On the biological line of the roughly 700 m3/day plant, we optimised aeration with an Aqualogic (Binder) system between 2023 and 2025. The plant's specific wastewater composition, including a cheese factory's discharge, and summer wastewater warming caused by climate change were particular challenges.

Outcome

Over two years, the client saved nearly HUF 6 million with almost no investment of its own effort.