FrieslandCampina – Carei
Pre-treatment of dairy wastewater by chemical flotation at FrieslandCampina's plant in Carei (Nagykároly), Romania, with a capacity of 600 m3/day.

Project overview
Treatment capacity
600
m3/day
Our role
Our sister company, INWATECH Ltd., acted as main contractor, handling permitting and implementation and running the trial operation.
01
The client
FrieslandCampina is the Netherlands-based Royal FrieslandCampina international dairy group, which operates dairy plants in several European countries.
02
The facility
The pre-treatment plant uses chemical flotation to reduce the pollutant load of the dairy wastewater before it is discharged. We took over the reference from our sister company when Water4All was founded in 2021 and took on the industrial segment.